How to install the complete set of organic fertilizer production equipment correctly?

2023/09/19
The organic fertilizer production line equipment includes: fermentation turner, crusher, feeder, horizontal mixer, organic fertilizer granulator, dryer, cooler, screening machine, weighing and packaging machine. The granulator includes npk fertilizer granulatordisc granulator machine, stock transfer granulator, etc. The fertilizer granulator machine price varies.

As a professional fertilizer equipment manufacturer, Huazhiqiang Heavy Industry has more than ten years of production experience. Today, we mainly introduce the installation process of organic fertilizer production equipment:
1. Before installation, check whether the basic dimensions of each installation meet the requirements of the drawings according to the plan and foundation drawings of the organic fertilizer production equipment. Inconsistencies should be repaired until each dimension is correct.
2. The installer should be familiar with the installation requirements of each organic fertilizer production equipment, and carry out construction in strict accordance with the technical requirements.
3. The organic fertilizer production equipment may be deformed, damaged or lost during transportation. Therefore, before installation, the equipment list should be checked and accepted, and corresponding measures should be taken to make the equipment in good condition before installation.
4. Before each organic fertilizer production equipment enters the installation site, it should be numbered, and the installation process card and schedule should be formulated, and transferred to the site for installation one by one according to the requirements of the installation process sequence.
Organic fertilizer production line equipment.
5. Installation sequence: from top to bottom, install the host equipment and rack position first, and then install the connecting pipes and electrical equipment.
6. Tools required for installation: The equipment and materials must be complete.
7. After the rotating parts of the organic fertilizer production equipment are installed, they must be flexibly rotated, without the sound of jamming and collision, and the connecting parts must be firmly sealed, without powder leakage, air leakage, oil leakage and other phenomena.
8. The installation of electrical equipment should comply with the relevant regulations, the direction of each line should be clear, there should be no electricity leakage, leakage, wires and cables should have protective shells to prevent mice from being bitten.
9. After all equipment is installed, each single machine should be tested with empty car, and the test run with load can be carried out after the operation is normal.
10. Before the test run, calibrate the electronic batching scale and packaging scale to meet the specified accuracy.
11. The load runs for 8 hours, and it can be handed over to the manufacturer for production and use after there is no fault.